Wednesday, August 18, 2010

PROCEDRUE FOR CLEANING SCHEDULE FOR QC DEPARTMENT

 1.0         PURPOSE
This SOP describes the cleaning schedule for QC Department
 2.0              RESPONSIBILITY

Administration department is responsible for cleaning activities of the QC Department. QC Head should ensure that the cleaning activities are done as per schedule

 3.0       PROCEDURE
a)       Floor                     :         Clean Twice a day
b)       Windows/ Walls     :         Clean Once in week
c)       Ceiling                  :         Clean once a month
d)      Instrument/ equipment tops and surrounding area – Daily
e)       Working bech Tops :         In evry shift,
f)         Reagent/ Solution bottles        :           Once in a day
g)       Chemicals/ reagent bottles in stock      :         Once in a month
h)       Sample trays          :         daily
i)       Sample Drawers               :         Once in week
The schedule is applicable for control sample room, instrument room as well
4.0       RECORD
Maintain the log of cleaning performed as per schedule

1 comment:

  1. sample tray should be wash every time before the sampling

    ReplyDelete