COMPUTERISED SYSTEM VALIDATION - Part 10
Prospective Validation - Deployment Phase On completion of successful testing the system is ready for installation into the final operational environment. During this phase the hardware and software installation is qualified and operational checks are performed. During this phase it is necessary to ensure that arrangements for the use and ongoing systems support and maintenance are either established or that documented plans have been prepared to ensure that these arrangements are in place when the system becomes operational. Data Load Plans, procedures and protocols should define the data load process. All GxP data should be at least double-checked to verify that it has been correctly loaded. Other checks should be put in place as required to verify original GxP data is correct. Statistical sampling can be used to check other data commensurate with the business need to verify data integrity. Rationales justifying sampling regimes should be defined. Automated data load tools should be ...