Flipkart

Monday, October 21, 2013

STANDARD OPERATING PROCEDURE FOR RECONCILIATION OF THE PACKING MATERIALS

1. OBJECTIVE
To describe the procedure for the accountability of the packing materials used for packing of a product.
2. SCOPE
The  procedure  is  applicable  for  reconciliation  of  the  packing  materials  after completion  of packing.
3. RESPONSIBILITY
Operator: To follow as per the written down procedure.
Packing Supervisor: To monitor and execute the written down procedure.
Head of Department: Implementation of the procedure
4. DEFINITIONS:
Nil
5. REFERENCES.
S.O.P. Guidelines
6. PROCEDURE
6.1. To know the quantities of all packing materials used after completion of a batch, below mentioned details are recorded in BMR.
6.1.1. Actual quantity issued.
6.1.2. Actual quantity used.
6.1.3. Quantity wasted or rejected on line.
6.1.4. Quantity  returned  to  Stores
6.1.5. Quantity of control  samples.
6.1.6. Quantity of reference sample.
6.1.7. Total of the above from 6.1.2  to  6.1.6.  which shall be equal to the quantity as per 6.1.1.  
7. RECORD                         : 
    Batch Manufacturing Record
8. Revision History

1 comment:

satish thube said...

What about the variance in reconciliation in BPR