1.0 OBJECTIVE
To lay down a procedure for transferring of machine under major break down.
2.0 SCOPE
Module -1,2,3,4 and 5.
3.0 RESPONSIBILITY
Production officer.
4.0 ACCOUNTABILITY
Executive / Sr. Executive.
5.0 PROCEDURE
5.1 Raise major breakdown request to maintenance through engineering helpdesk.
5.2 Transfer the machine to the respective module air lock.
5.3 Maintenance department transfers the machine from air lock to the repair bay.
5.4 Concerned production officer shall examine the machine after necessary repairs.
5.5 After getting clearance from concerned production officer, transfer the machine to the respective area.
Place the caution while in operation as follows
CAUTION:ENSURE NOT TO DAMAGE EPOXY FLOORING.